Municipal Composter Odor Control
Related Projects:    Plant Expansion   |   Custom Machinery   |   Water Treatment   |   Material Handling   |   Municipal Composter
Project Features
  • Compost cure pile structure and piping to collect odors
  • Process piping to collect odors from various composting equipment sources
  • Blowers in existing structure and new building
  • Packed tower scrubber
  • Biofilter
  • Site improvements

Services by JHI
  • Project Management
  • Mechanical Engineering
  • Civil Engineering
  • Structural Engineering
  • Electrical Engineering
  • Instrumentation Engineering
  • Construction Documents
  • Cost Estimatess
  • Operations and Maintenance Manual
  • Bidding Assistance
Project Cost
$1.8 Million

Project Completion
Design 2001
Construction 2004
Municipal Composter Odor Control
Wastewater Treatment Plant Composter Process Improvements for Odor Control

JHI prepared construction drawings, specifications, cost estimates, and an operations and maintenance manual for process improvements to control odors from a wastewater treatment plant composting operation. The improvements consisted of structures to contain odorous air and piping and blowers to collect odorous air from various sources, and odor treatment using a packed tower scrubber and biofilter. JHI’s design work included:
  • Process and piping design for odorous air collection
  • Facility design
  • Grading and paving
  • Metal building system specifications
  • Building foundations
  • Equipment and process piping installation
  • Ventilation system
  • Building and process electrical service
  • Instrumentation specification and tie-in to existing control system