Pollution Control System
Related Projects:    Truck Tippers   |   Paper Machine Wet End   |   Water Intake Structure   |   Pollution Control   |   Paper Machine
Project Features
  • Pollution control system for three boilers
  • Two 160-ft tall pile-supported towers
  • Ductwork and stack design
  • Underground utility relocation
Services by JHI
  • Project Management
  • Structural Engineering
  • Civil Engineering
  • Mechanical Engineering
  • Construction Documents
  • Cost Estimates
  • Permit Acquisition
  • Bidding Assistance
  • Construction Management
  • General Contractor
Project Cost
$10 million

Project Completion
2004
Pollution Control System
Pollution Control System Support Tower

With this $10 million turnkey project, JHI had the opportunity to utilize all of our talents to design, construct, and startup two pollution control systems to meet our client’s environmental permitting deadline. The project included structural, mechanical, and civil design. Effective project management allowed the multidiscipline team to create a readily constructible design within schedule and budget constraints.

Once the design was complete, JHI provided a complete range of construction services, including acting as the General Contractor. JHI’s knowledge of the design gave us a distinct advantage in hiring subcontractors and managing the construction. Familiarity with the project requirements allowed JHI to make sound and timely decisions, resulting in significant cost savings to our client.

This turnkey project highlights JHI’s ability to lead a project from start to finish. JHI has found that this design-build approach not only achieves the desired results in shorter periods of time but also results in cost savings to the client.